11th Circuit affirms delay damages award to subcontractor despite the existence of a “no-damages-for-delay” provision in the subcontractor agreement, finding that general contractor was aware of conditions causing delays and potential solutions, but did not enact those solutions. The opinion provides a thorough analysis of the types of damages awardable under these provisions and the causal link necessary to prove delay damages.
Read moreCourt Affirms $638,000 Award for Improper Stoppage of Construction Contract by County
Last week, Florida’s Second District Court of Appeal affirmed a $638,794.10 award for damages in favor of a utility contract, and reversed an award of $177,750 in liquidated damages in favor of the county that hired it. The damages awarded arose from an improper stoppage of work and delay in construction by the county.
Read more