11th Circuit Affirms Delay Damages Award to Subcontractor on Federal Project despite "No-Damages-For-Delay" Provisions in Contract

11th Circuit affirms delay damages award to subcontractor despite the existence of a “no-damages-for-delay” provision in the subcontractor agreement, finding that general contractor was aware of conditions causing delays and potential solutions, but did not enact those solutions. The opinion provides a thorough analysis of the types of damages awardable under these provisions and the causal link necessary to prove delay damages.

Read more

Court Affirms $638,000 Award for Improper Stoppage of Construction Contract by County

Last week, Florida’s Second District Court of Appeal affirmed a $638,794.10 award for damages in favor of a utility contract, and reversed an award of $177,750 in liquidated damages in favor of the county that hired it. The damages awarded arose from an improper stoppage of work and delay in construction by the county.