Last week, Florida’s Second District Court of Appeal affirmed a $638,794.10 award for damages in favor of a utility contract, and reversed an award of $177,750 in liquidated damages in favor of the county that hired it. The damages awarded arose from an improper stoppage of work and delay in construction by the county.
Read more