11th Circuit affirms delay damages award to subcontractor despite the existence of a “no-damages-for-delay” provision in the subcontractor agreement, finding that general contractor was aware of conditions causing delays and potential solutions, but did not enact those solutions. The opinion provides a thorough analysis of the types of damages awardable under these provisions and the causal link necessary to prove delay damages.